Ticket #1332 (closed assessed: fixed)
Values incorrectly shown as computed
Reported by: | sheilah | Owned by: | jeroens |
---|---|---|---|
Priority: | normal | Milestone: | Ecopath 6: future version |
Component: | Overall GUI | Version: | 6.4.1 |
Severity: | minor | Keywords: | |
Cc: |
Description
She uses a EE of 0.95 to estimate biomass for these groups… but when you balance (basic estimates) it puts the EE in blue for them … why is that? It indicates that it is estimated but it isn’t.
Change History
Note: See
TracTickets for help on using
tickets.
This is a generic issue which can occur for all output values in Ecopath. The comparison of input and output values may fail because of slight rounding errors. Instead, the code should check if the value was entered in the first place.